Table of Contents
Volumen I
Part 1
Instructions to Tenders
Part 2
Tender Forms
Part 3
Forms of Security
A16Part 4
(Not Used)A16
Part 1
Locks Performance and Design Criteria

Locks Project Main Performance Requirements

Part 2
Supplemental Requirements

Locks Systems Performance Requirements

Part 3
General Requirements
Part 4
Requirement Drawings
Conditions of Contract
Employer’s Evaluation Criteria
General and Administrative
Part 1
Overall Execution Plan
A16Part 2
Key PersonnelA16
A7Part 3
(Not Used)A7
Technical
Part 4
Design-Build Execution Methodology
Part 5
Design Plan
Part 6
Construction Plan
Part 7
A19Maintenance ServicesA19
Part 8
Training of ACP Personnel
A7Part 9
Price ProposalA7
Contractor’s Proposal (Instructions)A16
General and Administrative
Part 1
Overall Execution Plan
A16Part 2
Key PersonnelA16
A7Part 3
(Not Used)A7
Technical
Part 4
Design-Build Execution Methodology
Part 5
Design Plan
Part 6
Construction Plan
Part 7
A19Maintenance ServicesA19
Part 8
Training of ACP Personnel
A7Part 9
Price ProposalA7
Reference Douments
Part 1
Reference Drawings
A7Part 2
Geotechinical Reports
A16Part 3
Seismic Data for Temporary StructuresA16
Part 4
A11Environmental ReportsA11
Part 5
Conceptual Design of Post Panamax Locks (Pacific) (CPP, May 2003)
Part 6
Update of Pacific Locks Conceptual Design and Harmonization of Atlantic Locks Conceptual Design (CPP, May 2005)
Part 7
Hydrometeorological Report
Part 8
A19Filling and Emptying Systems Reference DocumentsA19
Part 9
Handbook of Lockage Procedures (existing locks)
Part 10
Blasting Records
Part 11
Widening and Deepening of the Pacific Entrance and South Approach Channel to the Third Set of Locks of The Panama Canal (including drawings)
Part 12
Feasibility Evaluation of a Tug Assisted Locks Vessel Positioning System
Part 13
Tugboat Fleet Principal Particulars
Part 14
A19Design [Specification and Drawings] for East Barrier Dam 2E, West Barrier Dam 1W and West Barrier Dam 2W StructuresA19
Part 15
Programa de Ampliación del Canal: Canal de Aproximación Norte Pacífico Proyecto No. PAC-2 (including drawings)
A11Part 16
Electrical Works Reference DataA11
A11Part 17
Miraflores Swing Bridge Reference DocumentsA11
A16Part 18
Gatun Lake Dump Sites Bathymetric DataA16
A16Part 19
AdministrativeA16
A19Part 20
Traffic ScenariosA19
Employer’s Data
Part 1
Geotechnical Interpretive Report
Part 2
Topographical Data
Part 3
Seismic Design Criteria Data:

Accelerations and Response Spectra